4 Tracks

CTC will have four tracks - one turf course, two all-weather tracks and one uphill turf gallop.

150 Hectares

More than twice the size of Sha Tin Racecourse and its stable complexes.

11,000,000 m3

11 million cubic metres of earth were moved to accommodate CTC.

Timeline

2017

July 2017

Large and small all-weather dirt track installation completed

2017

May 2017

Turf course installation completed

Turf course installation completed
2017

March 2017

CTC construction site surpassed 600 million safe working hours

2017

January 2017

CTC pre-opening office officially opened

CTC pre-opening office officially opened
2016

September 2016

Turf installation commenced on 2000-metre course

2016

April 2016

First Mainland Work Rider recruitment campaign in Guangzhou

2016

March 2016

First trial of cross-border movement of horses between Hong Kong and the Chinese Mainland completed successfully

First trial of cross-border movement of horses between Hong Kong and the Chinese Mainland completed successfully

FAQ

When will CTC open?

CTC is scheduled to open for the training of Hong Kong horses from August 2018.

Where can I stay when visiting CTC?

The Conghua area has a variety of hotels catering to all tastes, including several with hot springs. CTC is located about one hour from Guangzhou for those wishing to stay in the city.

What horses will go to CTC?

Trainers will determine which of their horses are based at CTC.

Are there any changes to livery charges for horses at CTC?

No. The monthly livery charge remains the same regardless of where a horse is based.